ACC administration provided a proposed timeline for the 2022 General Obligation (GO) bond program to trustees at the regular May board meeting.
The college plans to roll out the bond projects in three phases with all 13 projects planned to be completed by 2029.
2023-2027
Round Rock Campus
Hays Campus
Southeast Travis Campus
Pinnacle Campus
2024-2028
Rio Grande Campus
Highland Campus
Eastview Campus
Northridge Campus
Riverside Campus
South Austin Campus
2025-2029
Cypress Creek Campus
Elgin Campus
San Gabriel Campus
The College will also retain third-party program managers to help manage some of the Bonds projects.
Next Steps
Administration also shared an update on the next steps:
June
– Board selection of the Architecture & Engineering Team for Hays Campus
– Board selection of the Architecture & Engineering Team for Southeast Travis County
– Board selection of the Construction Manager for Round Rock Campus: Applied Technology Expansion
– Issue bonds
July
– Board selection of the Construction Manager for Hays Campus
– Board approval of the Program Management Services firms
– Bond Preliminary Official Statement
– Bond order
August
– Board selection of the Architecture & Engineering Team for Pinnacle Campus
– Board selection of the Construction Manager for Southeast Travis County Campus