Austin Community College District’s (ACC) Round Rock Campus Student Support Center project has reached a key milestone, with Phase 2 of the renovation now substantially complete. The work is part of the College’s ongoing Maintenance and Operations Bond projects.

Owner move-in is already underway. New furniture and office equipment are being installed this week, and Student Affairs staff are expected to relocate to their new offices after winter break. The updated space will be ready to support students for the spring semester, providing modern, functional areas designed to enhance student services and access.

Phase 3 of the project is currently under construction and is approximately 40% complete. In-wall rough-in for electrical and telecommunications systems has been finalized, and drywall installation is now underway after passing inspections with the City of Round Rock. Overhead mechanical and electrical work continues as progress moves forward.

Phase 3 is expected to be completed toward the end of February 2026. This phase will introduce a new Career Center/Make It Center, located between the newly opened Welcome Center and the Student Affairs Suite that are part of Phase 2. Construction will continue through winter break to keep the project on schedule.

Once complete, the Student Support Center will centralize key student services — creating a seamless, student-focused experience on the Round Rock Campus.