Photo above shows offices, the Inspiration Hub (covered glass and pink insulation), ACC Showcase space (area next to the Inspiration Hub), and the interactive digital experience wall (wood wall)
Construction continues on the Make It Center at ACC Highland Campus. The project is scheduled to be completed by the end of the fall semester.
The following update has been provided by Dr. Janelle Green, ACC Make It Center director:
Drywall was installed and finished in August and painting is now underway. 90% of the overhead electrical service installations are complete. Crews also have installed the frames for bench seating in the showroom. Work is now underway to install new, raised flooring in the area as well as acoustical ceiling treatments, lighting, and carpet. Concrete polishing is ongoing and woodwork within the space has begun.
Furniture specifications and fabrics are finalized, and a majority of the furniture under $30,000 has been ordered. The process to purchase and install more expensive furniture and equipment needs is underway.
The following team members have been hired since the spring: Operations and Guest Experience Manager Mary Roby, Programming Manager Adrian Perez, IT/AV Manager Tim Outlaw, and, most recently, Programming Coordinator AJ Mays.
The Make It Center team is developing the inaugural showcase plan. ACC areas identified for the first showcase include:
- Creative Arts/Digital Media/RTF;
- CE and Fast Track Programs;
- Culinary/Hospitality/Tourism;
- CIS/IT/Cybersecurity; and
- Drones (connected to many careers and Business & Industry).
The college continues to work with potential programming partners to provide enhanced support services. Those partners include:
- CapMetro
- Indeed
- Texas Commission on Environmental Quality
- ACC College and High School Relations
- ACC Bioscience Incubator
- ACE Academy
- CareerLabs
- TransfrVR
Learn more about the center here and view the last update from summer 2022 here.